Pre-Opening Hotels: Working Back From Opening Day to Your Order Date

November 10, 2026
3 MIN READ
3 diagrams
Pre-Opening Hotels: Working Back From Opening Day to Your Order Date
In this article
  1. The countdown
  2. The steps people leave out
  3. What to order for opening
  4. If the opening date moves
  5. If you are already late
  6. Plan yours

Short answer: start sampling about 18 weeks before opening for a Gulf hotel and about 21 weeks for a European one. The order itself, with the advance paid, should be placed 14 to 18 weeks out. Linen has to arrive three weeks before the first guest, not the day before.

Weeks before opening day
18
start sampling, Gulf hotel
21
start sampling, European hotel
16
order and advance, latest
3
linen on site before the first guest

The countdown

Counting back from opening day
18 to 20 weeks out
Compare quotes, fix the specification
16 to 18 weeks
Samples made, tested, approved
10 to 16 weeks
Production, 30 to 45 days
6 to 9 weeks
At sea
5 weeks
Customs clearing
4 weeks
Delivered to the hotel
3 to 1 weeks
First wash, count, rooms made up
Day 0
Opening day
Weeks before openingWhat should be happening
3 to 1Linen washed, counted into the store, rooms made up, staff trained
4Goods delivered to the hotel
5Customs clearing and delivery
6 to 9At sea: about 2 weeks to the Gulf, about 4 to Europe, including port time
10 to 16Production, 30 to 45 days
16 to 18Samples made, shipped, tested and approved
18 to 20Quotes compared and specification finalised

For a Gulf hotel, the steps total about 18 weeks. For a UK or EU hotel, about 21.

The steps people leave out

The first wash of all new linen
Room setup and snagging
The mock-up room
Brand approval of the spec
Customs on a first import
  • The first wash. New linen must be washed before use. For a 150-room hotel that is several tonnes through a laundry that may itself be brand new.
  • Room setup and snagging. Housekeeping needs made-up rooms for training, photography and inspections.
  • Mock-up room. The owner and brand usually approve one finished room. Linen samples for it are needed months ahead.
  • Brand approval. If the hotel carries a brand flag, the brand standard may need to sign off the spec.
  • Customs surprises. A first import by a new company can be held for paperwork.

What to order for opening

Opening stock is your par level, usually three sets per bed and per bathroom, plus a margin for loss in the chaotic first weeks. Work it out with the par level calculator, and see the towel sum in how many towels a hotel needs.

Order robes, towels, bath mats and bed linen together where you can. They arrive together and the whites match. See robes and towels on one order.

If the opening date moves

Opening dates slip more often than they hold. Two things help:

  • Tell your supplier the earliest and latest dates, not only the target.
  • Arrange storage at the hotel or with your forwarder for linen that arrives before the building is ready. Storing linen for a month costs far less than opening without it.

If you are already late

  • Split the order: air freight one par for opening, and send the rest by sea.
  • Choose white and standard sizes. Custom colours and embroidery add time.
  • Use running sizes where they fit your spec. See ordering fewer than 500 towels.

Plan yours

The order planner on the production capacity page gives your order-by date from an opening date. Gulf projects should also read the Saudi hotel opening linen checklist. When you have a room count and a date, ask us for a quote.

Share this article

#Pre-Opening
#Hotel
#Lead Time
#Order Planning
#OS&E

Want pricing on what you just read?

Leave your work email — our export desk replies with specs, MOQ and a quote within 1 business day.

Dr Abin Babu

Written by

Dr Abin Babu

Founder & Chairman, Anabyn Global Ventures

Anabyn exports hotel and home linen from Kerala, India. These guides come from the questions buyers ask our desk. About the team

Ready to Order?

Send us your specification. We reply within one business day and send a priced quote within 48 hours.

Request an Export Quote