Short answer: production takes 30 to 45 days from your advance payment. Then the goods are inspected, you pay the balance, and they sail from Cochin. A Gulf buyer has goods at port about 8 weeks after approving the sample. A UK or EU buyer should plan 10 to 11 weeks.
The timeline
| When | What happens | What you see |
|---|---|---|
| Day 0 | You approve the sample and the spec | A signed spec sheet and proforma invoice |
| Days 1 to 3 | You pay the 50 percent advance | Payment receipt, order confirmation with a ship date |
| Week 1 | Yarn is booked, labels and cartons ordered | Label and carton artwork for your approval |
| Weeks 2 to 3 | Weaving | A progress update |
| Weeks 3 to 4 | Dyeing or bleaching, washing | Shade checked against the approved sample |
| Weeks 4 to 5 | Cutting, hemming, embroidery, labels | Photos of first finished pieces |
| Weeks 5 to 6 | Final inspection to AQL 2.5, packing | Inspection report and production photos |
| After inspection | You pay the 50 percent balance | Balance invoice |
| Dispatch | Goods move to Cochin and are loaded | Bill of lading, invoice, packing list, certificate of origin |
Each stage runs at a specialist unit, and we check the goods at every handover. Our post on how one order moves through six specialist units explains who checks what.
Then the sea leg
| Destination | Sea transit from Cochin |
|---|---|
| UAE | 7 to 10 days |
| Saudi Arabia | 8 to 12 days |
| UK | 21 to 26 days |
| Germany | 22 to 28 days |
| Australia | 18 to 25 days |
| US West Coast | 18 to 22 days |
Add a few days at each end for port handling and customs.
What can stretch it
- Late artwork. Labels and embroidery files approved in week 3 instead of week 1 push everything back.
- Custom colours. A new shade needs a lab dip approved before dyeing starts.
- Changes after the advance. A new size or weight restarts the yarn booking.
- Holidays and monsoon. See shipping linen in the monsoon.
What you should do in those weeks
- Approve artwork within two days of receiving it.
- Appoint your customs broker and send us their details.
- Decide whether you want your own inspector, and book them for week 5.
- Arrange the balance payment so it does not delay dispatch.
Check dates before you order
Our production capacity page has an order-by planner that works back from the date you need the goods. Once an order is running you can follow it on the tracking page. To start, request a quote with the date you need delivery.
Share this article
Want pricing on what you just read?
Leave your work email — our export desk replies with specs, MOQ and a quote within 1 business day.

Written by
Dr Abin Babu
Founder & Chairman, Anabyn Global Ventures
Anabyn exports hotel and home linen from Kerala, India. These guides come from the questions buyers ask our desk. About the team
Ready to Order?
Send us your specification. We reply within one business day and send a priced quote within 48 hours.
Request an Export QuoteWhere to go next